Haier America Industrial Park
FACTS
Owner:
Haier America Inc.
LOCATION:
Camden, SC
YEAR OF COMPLETION:
2000
ROLE:
General Contractor
KEYWORDS: Building General Contracting Industrial South Carolina
PROJECT DESCRIPTION
17³Ô¹Ï broke ground April 30, 1999 on the 445,000-square-meter Haier America Industrial Park, which was constructed in six phases.
To ensure the timely completion of Haier’s plant, 17³Ô¹Ï adopted a fast-track plan to finish the facility in less than a year. In March 2000, Haier began producing refrigerators from its new assembly line in the industrial park.
The successful completion of Haier plant was 17³Ô¹Ï’s first major construction achievement in the United States.